Education

University Center Lobby and Charger Café – The University of Alabama in Huntsville

  • Project Description: 
    • 5,300 sf addition and existing building renovation
  • Structural Components: 
    • Deep and shallow foundations, reinforced concrete retaining walls, precast architectural panels, and structural steel
  • Construction Cost:  
    • $3.1M
  • Construction Completion:  
    • 2007

Austin High School Science Building – Decatur, Alabama

  • Project Description:
    • New two-story 45,600 sf school building
  • Structural Components:
    • Reinforced concrete, reinforced masonry, structural steel, bar joists, and precast hollow core elevated slabs
  • Construction Cost:
    • $7M
  • Construction Completion: 
    • 2007

The Country Day School – Huntsville, Alabama

  • Project Description:
    • New 19,300 sq single story private school
  • Structural Components:
    • Structural steel, reinforced concrete, reinforced masonry, conventional wood framing, and heavy timber framing
  • Construction Cost:
    • $2.2M
  • Construction Completion: 2003

Hartselle High School – Hartselle, Alabama

  • Project Description:
    • New two-story 255,000 sf high school including classrooms, labs, offices, two gymnasiums, cafeteria, media center, auditorium, two storm shelters, and adjacent 10,000 sf field house.
  • Structural Components:
    • Reinforced masonry, precast hollow core elevated slabs, pre-fabricated metal roof trusses, structural steel, steel bar joists, and reinforced concrete walls
  • Construction Cost:
    • $38M
  • Construction Completion:
    • Spring 2012

Priceville High School – Priceville, Alabama

  • Project Description:
    • New 157,000 sf high school including classrooms, labs, shops, media center, cafeteria, two gymnasiums, storm shelter, and adjacent 14,000 sf field house.
  • Structural Components:
    • Reinforced masonry, pre-fabricated metal roof trusses, structural steel, steel bar joists, and reinforced concrete walls.
  • Estimated Construction Cost:
    • $19M
  • Estimated Construction Completion:
    • August 2015

Back to Projects